The Savings Math: VMI vs. Ordering on Your Own

VMI saves money in four places: staff hours, purchase order costs, carrying costs, and stockouts. Add them up with your own numbers, and you have a dollar figure you can take to your plant manager. Here is the worksheet, with an example plant.

 

“It sounds nice” won’t get VMI approved. A dollar figure will. Use this worksheet with your own numbers.

The Four Savings

Savings

How to calculate it

Example plant

Staff hours

Hours per week on packaging x loaded rate x 52

4 hrs x $30 x 52 = $6,240

Purchase orders

Orders per year x cost per order ($14 to $54+)

120 x $35 = $4,200

Carrying cost Stock removed x 25%

$20,000 x 25% = $5,000

Stockouts

Last year’s stockout costs (labor, freight, lost output)

2 stockouts x $1,500 = $3,000

Total

$18,440 a year

Where the Example Numbers Come From

  • Staff hours: one person spending half a day a week on counting and ordering.
  • Purchase orders: 10 packaging orders a month at the middle of the APQC range.
  • Carrying cost: a third less stock on $60,000 of packaging, carried at 25% a year.
  • Stockouts: two short line stops with rush freight. Your number may be much higher.

What VMI Costs

Ask any supplier offering VMI whether counts, reporting, or minimum orders carry a fee, and subtract that cost from the total.

Run the Numbers

  1. Fill in each row with your plant’s numbers.
  2. Leave a row blank if you don’t know it, and add it later.
  3. Compare the total with any VMI fee your supplier quotes.

Ready to Start?

Send us your worksheet, even half-filled, and we’ll fill in the gaps with you.